Fairburn to River Aire Outfall Drainage Scheme.        Nov 2007 to April 2008

1.5 km Upgrade to the Fairburn Drainage System mostly through a totally residential area.

The works involved the checking, reporting and recording of all works for the Client. The 600mm drainage pipes were required to be installed to strict line and level parameters, as were the numerous manholes. A river outfall with associated retaining walls had to be constructed and there were onerous reinstatement clauses placed on the Contractor.

 